Place | Date | Hour | Summary | Reference |
---|---|---|---|---|
WYKE REGIS | 1-10 | Nothing to record. | ||
MADINGLEY | 11 | Collection of 2 Austin utilities from 21 VRD. Also 1 4 str 4×2 Ford car. | ||
12 | Return from WYKE REGIS to MADINGLEY. Admin Order No 2. | Appendix “A” | ||
16 | 0900 | Visit to this HQ by C.E. Eastern Command. | ||
18 | 1200 | Admin Order No 1 “Marathon II” issued. | Appendix “B” & “C” | |
18 | Exercise – “Marathon II” | |||
20 | 0900 | Advance party (Adj & 2 O.Rs) leave for NORTH MUSKHAM. | ||
21 | 0830 | Main H.Q. leaves for NORTH MUSKHAM, arrives 1730 hrs. | ||
NORTH MUSKHAM | 22 | Locations: H.Q.: 270788 (& det. 211) 11: 270788 209: 2876 210: 256785. | Ref Map O.S. 1”-1m Sh ? 46 | |
22 | Progress reports from 11 Fd Coy:- | |||
22 | 0940 | Lorries arrive on site. | ||
22 | 1100 | Unloading completed. | ||
22 | 1210 | Bridging started. | ||
22 | 1500 | Construction 5%: approaches started. | ||
22 | 1700 | Construction 25%: approaches started. | ||
23 | 1015 | Construction 75%: approaches 50%. | ||
23 | 1100 | Construction 75%: approaches 60%. | ||
23 | 1200 | Construction 75%: approaches 90%. | ||
23 | 1900 | Exercise Marathon II Phase II Op Order ? 1 issued. | App “D” | |
23 | 1400 | Construction 85%. | ||
23 | 1500 | Constructions complete less ramps & jacking down near bank. | ||
23 | 1610 | Bridge open to traffic. | ||
EASEDIKE | 24 | 1200 | H.Q. moves to EASEDIKE 947652. | |
24 | Progress reports 210 Fd Coy (R WHARFE). | |||
24 | Location 210 943637 with following u/c 1 sec PRO, 1 sec F.B.E., 1 bailey pl, half a raft pl. | |||
24 | 1800 | Lorries on site. | ||
24 | 2000 | 85% complete. | ||
24 | 2100 | Sommerfelt complete. | ||
24 | 2300 | Work ceases. | ||
25 | 0820 | Estimated time of completion 1300 hrs. | ||
25 | 1040 | Half raft pl. arrived NEWTON KYME 3364 and work commences on ferry below F.B.E. site at 1400 hrs. | ||
25 | 1000 | F.B.E. 50% complete and one pl crossing. | ||
25 | 1100 | F.B.E. 80% complete estimated time of completion 1200 hrs. Work started on Bailey site at CATTAL. | ||
25 | 1300 | F.B.E. bridge now open to traffic. Bailey launching nose complete. | ||
25 | 1400 | Work starts on batwing ferry. | ||
25 | 1500 | Ferry 20% complete. Bailey four bays built completion advanced 2000 hrs. | ||
25 | 1800 | Ferry completed. Bailey 60% complete. Work finishes. | ||
25 | 1900 | Exercise Canute. Preliminary Instructions issued. | App ‘E’ | |
25 | Phase III Op Order ? 2 issued. | App ‘F’ | ||
26 | 1100 | Sitrep 210: Bailey 75% complete estimated time of completion 1400 hrs. | ||
26 | 1200 | Bailey 80% complete. | ||
26 | 1300 | Bailey 90% complete. | ||
26 | 1337 | Cl 40 Br. CATTAL E922742 open to traffic. | ||
26 | 1501 | 209 reports recce of R. URE & R. SWALE. Proposed F.B.E. bridge at BRIDGE HAWICK 808904 and Bailey bridge at SKELLFIELD SCHOOL 864964. Mines found. | ||
26 | 1600 | C.E. visits H.Q.R.E. | ||
27 | 1300 | Sitrep from 209 located BISHOP MONKTON 8086. F.B.E. bridge home side approach 80% complete. Home side trestle and half-floating bay cpte. 2 trestles ferried to far side. 1 floating bay cpte. Estimated completion 1800 hrs. | ||
LITTLE OUSEBURN | 27 | 1500 | H.Q.R.E. moves to KIRBY HALL FARM 928805. | |
27 | 1755 | F.B.E. Bride 85% complete. Gap 1’3” too short. Estimated time of completion 2000 hrs. | ||
28 | 0900 | Sitrep from 209: F.B.E. completed 1910 hrs 27. Bailey SKELL FIELD SCHOOL bank seats 80% complete. | ||
28 | 1100 | Nose complete. Bridge started: far bank seat 80% estimated time of completion 1800 hrs. | ||
28 | 1500 | Bailey Bridge 80% complete estimated time of completion 1730 hrs. | ||
28 | 1820 | Bailey Bridge open to traffic 1820 hrs. | ||
28 | 1900 | Op. Order ? III issued. | App ‘H’ | |
29 | 1000 | H.Q.R.E. moves to GRINGLEY-ON-THE-HILL A215101. 210 located A231146. 11 located 279111. Br Trent at WALKERITH. |